ICICI Bahrain โ TM Efficacy Engagement
11-week AML TMS efficacy engagement for ICICI Bank Bahrain. 5 workstreams across data audit, coverage assessment, segmentation design, threshold calibration, and rule advisory against AMLOCK.
Start
11 Jun 2026
Target
12 Aug 2026
Duration
61 days (11 weeks)
Week
Week 3 of 11
Days elapsed
15 of 61 days
Days to go
46d
Engagement Timeline
Expected position (25%)
Actual progress (9%)
Project is 16% behind expected pace
At Week 3 of 11, the engagement should be 25% complete. Actual progress is 9%. The gap is driven by 0 issues blocked at ICICI Bank Bahrain, including the engagement kick-off and all 0 required data files.
Delay Attribution
Held by: ICICI Bank Bahrain (Client)
The engagement cannot progress because ICICI Bank Bahrain has not yet provided data access or the 0 required data files. The engagement kick-off itself is blocked pending this access.
0 Data Files Not Received
Expected by Today โ Week 3
Based on a standard 11-week AML engagement timeline, the following should be in progress or completed by Week 3. Items still blocked or unstarted indicate a schedule risk.
๐กTo-Do
Define ongoing data quality controls and produce Sanctions Field Completeness Report
To-Do โ behind expected schedule ยท WS1 ยท Data Audit
๐กTo-Do
Classify all ICore field gaps by severity and assign remediation routes
To-Do โ behind expected schedule ยท WS1 ยท Data Audit
๐กWaiting on ICICI
Validate inward/outward transaction classifications and product-to-segment mappings
Waiting on ICICI โ behind expected schedule ยท WS1 ยท Data Audit
๐กIn Progress
Assess ICore โ AMLOCK data completeness โ join keys and residency flags
In Progress โ behind expected schedule ยท WS1 ยท Data Audit
๐กWaiting on ICICI
Engagement kick-off โ confirm data access and technical contact
Waiting on ICICI โ behind expected schedule ยท Engagement Setup
All Tasks (36)
In Progress13
Planned โ Not Yet Started23
Engagement close โ compile and hand over full deliverable packHighTo-Do20d ago
Final deliverable review session with ICICI Bank BahrainHighTo-Do20d ago
Rule rationalisation โ merge candidates and deletion candidatesHighTo-Do20d ago
New scenario design โ Anticipated Profile DeviationMediumTo-Do20d ago
New scenario design โ Terrorist Financing DetectionHighTo-Do20d ago
New scenario design โ Trade Finance MonitoringMediumTo-Do20d ago
New scenario design โ Post-STR Enhanced MonitoringHighTo-Do20d ago
New scenario design โ NRI Enhanced MonitoringHighTo-Do20d ago
CR-ready modification recommendations โ all 13 live rulesHighTo-Do20d ago
Final simulation run โ confirm optimal thresholds and produce UAT test casesUrgentTo-Do20d ago
P50โP90 percentile analysis and segment-specific calibration โ all 13 live rulesUrgentTo-Do20d ago
Establish performance baseline for all 13 live rulesUrgentTo-Do20d ago
Define segment-specific threshold parameters and produce AMLOCK implementation reportMediumTo-Do20d ago
Define segment flag specifications for AMLOCK implementationHighTo-Do20d ago
Design customer segmentation framework โ tiers and cross-border corridorsHighTo-Do20d ago
Smell Test โ qualitative sanity check across all 26 rulesishikaHighTo-Do19d ago
Document full configuration of all 13 live rules โ Scenario Configuration CatalogueprekshaUrgentTo-Do18d ago
Repeated Alert Analysis โ same-rule and cross-rule repeatersishikaHighTo-Do19d ago
Assess design completeness and implementation readiness of 13 pipeline rulesHighTo-Do0d ago
Identify unmonitored customer populations and productsHighTo-Do0d ago
Map all 26 rules against customer segments, products, and jurisdictions โ RAG-rate eachUrgentTo-Do0d ago
Define ongoing data quality controls and produce Sanctions Field Completeness ReportHighTo-Do0d ago
Classify all ICore field gaps by severity and assign remediation routesHighTo-Do0d ago
Workstream Status
0
Blocked
13
Active
23
Planned
0
Delivered
WS1 ยท Data Audit
Data reconciliation, quality checks, field gap analysis
2 in progress2 planned
WS2 ยท Rules Coverage
26-rule assessment, configuration catalogue, noise analysis
9 planned
WS3 ยท Segmentation
Customer segmentation framework and AMLOCK flag design
3 planned
WS4 ยท Calibration
Threshold tuning, percentile analysis, simulation & UAT
1 planned
Advisory / New Scenarios
CR recommendations, new scenario design, rule rationalisation
6 planned
Deliverables
Formal deliverable packs and review sessions
2 planned
Deadline
12 Aug 2026
46 days remaining
Progress9%
Expected: 25%โ16% behind