Optimoney/PortfolioICICI Bank Bahrain
Fri, 26 June 2026
9%done

ICICI Bahrain โ€” TM Efficacy Engagement

11-week AML TMS efficacy engagement for ICICI Bank Bahrain. 5 workstreams across data audit, coverage assessment, segmentation design, threshold calibration, and rule advisory against AMLOCK.

Active
Start
11 Jun 2026
Target
12 Aug 2026
Duration
61 days (11 weeks)
Week
Week 3 of 11
Days elapsed
15 of 61 days
Days to go
46d
Engagement Timeline
W1W2W3W4W5W6W7W8TODAY11 Jun 202612 Aug 2026
Expected position (25%)
Actual progress (9%)
Project is 16% behind expected pace
At Week 3 of 11, the engagement should be 25% complete. Actual progress is 9%. The gap is driven by 0 issues blocked at ICICI Bank Bahrain, including the engagement kick-off and all 0 required data files.
Delay Attribution
Held by: ICICI Bank Bahrain (Client)
The engagement cannot progress because ICICI Bank Bahrain has not yet provided data access or the 0 required data files. The engagement kick-off itself is blocked pending this access.
0 Data Files Not Received
Expected by Today โ€” Week 3
Based on a standard 11-week AML engagement timeline, the following should be in progress or completed by Week 3. Items still blocked or unstarted indicate a schedule risk.
๐ŸŸก
Define ongoing data quality controls and produce Sanctions Field Completeness Report
To-Do โ€” behind expected schedule ยท WS1 ยท Data Audit
To-Do
๐ŸŸก
Classify all ICore field gaps by severity and assign remediation routes
To-Do โ€” behind expected schedule ยท WS1 ยท Data Audit
To-Do
๐ŸŸก
Validate inward/outward transaction classifications and product-to-segment mappings
Waiting on ICICI โ€” behind expected schedule ยท WS1 ยท Data Audit
Waiting on ICICI
๐ŸŸก
Assess ICore โ†’ AMLOCK data completeness โ€” join keys and residency flags
In Progress โ€” behind expected schedule ยท WS1 ยท Data Audit
In Progress
๐ŸŸก
Engagement kick-off โ€” confirm data access and technical contact
Waiting on ICICI โ€” behind expected schedule ยท Engagement Setup
Waiting on ICICI
All Tasks (36)
In Progress13
AMLOCK NRISR Transactions
Waiting on ICICI
NRISR Transations
Waiting on ICICI
NRISR Customer Data
Waiting on ICICI
ICORE Transactions Data
Waiting on ICICI
AMLCOK Transaction Data
Waiting on ICICI
AMLOCK Accounts Data
Waiting on ICICI
ICORE Accounts Data
Waiting on ICICI
AMLOCK Customer Data
Waiting on ICICI
ICORE Customer Data
Waiting on ICICI
Identify field-level gaps in ICore โ€” 12 critical TM fields
Waiting on ICICI
Validate inward/outward transaction classifications and product-to-segment mappings
Waiting on ICICI
Assess ICore โ†’ AMLOCK data completeness โ€” join keys and residency flags
In Progress
Engagement kick-off โ€” confirm data access and technical contact
Waiting on ICICI
Planned โ€” Not Yet Started23
Engagement close โ€” compile and hand over full deliverable packHighTo-Do20d ago
Final deliverable review session with ICICI Bank BahrainHighTo-Do20d ago
Rule rationalisation โ€” merge candidates and deletion candidatesHighTo-Do20d ago
New scenario design โ€” Anticipated Profile DeviationMediumTo-Do20d ago
New scenario design โ€” Terrorist Financing DetectionHighTo-Do20d ago
New scenario design โ€” Trade Finance MonitoringMediumTo-Do20d ago
New scenario design โ€” Post-STR Enhanced MonitoringHighTo-Do20d ago
New scenario design โ€” NRI Enhanced MonitoringHighTo-Do20d ago
CR-ready modification recommendations โ€” all 13 live rulesHighTo-Do20d ago
Final simulation run โ€” confirm optimal thresholds and produce UAT test casesUrgentTo-Do20d ago
P50โ€“P90 percentile analysis and segment-specific calibration โ€” all 13 live rulesUrgentTo-Do20d ago
Establish performance baseline for all 13 live rulesUrgentTo-Do20d ago
Define segment-specific threshold parameters and produce AMLOCK implementation reportMediumTo-Do20d ago
Define segment flag specifications for AMLOCK implementationHighTo-Do20d ago
Design customer segmentation framework โ€” tiers and cross-border corridorsHighTo-Do20d ago
Smell Test โ€” qualitative sanity check across all 26 rulesishikaHighTo-Do19d ago
Document full configuration of all 13 live rules โ€” Scenario Configuration CatalogueprekshaUrgentTo-Do18d ago
Repeated Alert Analysis โ€” same-rule and cross-rule repeatersishikaHighTo-Do19d ago
Assess design completeness and implementation readiness of 13 pipeline rulesHighTo-Do0d ago
Identify unmonitored customer populations and productsHighTo-Do0d ago
Map all 26 rules against customer segments, products, and jurisdictions โ€” RAG-rate eachUrgentTo-Do0d ago
Define ongoing data quality controls and produce Sanctions Field Completeness ReportHighTo-Do0d ago
Classify all ICore field gaps by severity and assign remediation routesHighTo-Do0d ago
Workstream Status
0
Blocked
13
Active
23
Planned
0
Delivered
WS1 ยท Data Audit
Data reconciliation, quality checks, field gap analysis
4 issues
2 in progress2 planned
WS2 ยท Rules Coverage
26-rule assessment, configuration catalogue, noise analysis
9 issues
9 planned
WS3 ยท Segmentation
Customer segmentation framework and AMLOCK flag design
3 issues
3 planned
WS4 ยท Calibration
Threshold tuning, percentile analysis, simulation & UAT
1 issues
1 planned
Advisory / New Scenarios
CR recommendations, new scenario design, rule rationalisation
6 issues
6 planned
Deliverables
Formal deliverable packs and review sessions
2 issues
2 planned
Deadline
12 Aug 2026
46 days remaining
Progress9%
Expected: 25%โˆ’16% behind